AHERA asbestos management required
This building was constructed in 1968, before 1981. Federal law (AHERA) requires a triennial re-inspection every 3 years, a 6-month periodic surveillance walkthrough, and an annual notification letter to all parents and staff. Penalty: up to $25,000/day for non-compliance.
Annual Fire Extinguisher Inspection
OverdueNFPA 10 / IFC 906.2All portable fire extinguishers must be inspected annually by a certified contractor per NFPA 10.
Sprinkler System Semi-Annual Test
Due SoonNFPA 25Wet pipe sprinkler system inspection and flow test per NFPA 25.
AIM Act Refrigerant Leak Detection Installation
Due SoonEPA AIM Act HFC Management Rule (2026)EPA AIM Act HFC Management Rule requires automatic leak detection on systems ≥15 lbs refrigerant charge by Jan 1, 2027.
WA CBPS Tier 2 Energy Benchmarking
OverdueWA CBPS Tier 2 / HB 1257 Expansion 202242,000 sq ft school — Tier 2 building. Must benchmark and implement O&M program by July 1, 2027.
AHERA Asbestos 3-Year Re-inspection
OverdueEPA AHERA / 40 CFR Part 763All K-12 schools must conduct asbestos re-inspections every 3 years per AHERA. Fines up to $25,000/day for non-compliance.
AHERA 6-Month Periodic Surveillance
OverdueAHERA — 40 CFR Part 763Periodic surveillance of all asbestos-containing materials by AHERA-accredited inspector. Required every 6 months.
Lead in Drinking Water Testing
Due SoonRCW 43.70.830 — Lead in School Drinking Water5-year testing cycle required for all K-12 schools. Community notification required after results per RCW 43.70.835.
Indoor Air Quality Assessment
Due SoonWAC 246-370 — Indoor Air QualityAnnual IAQ walkthrough and assessment. Air Quality Response Plan required for wildfire smoke and HVAC failure events.
IPM Annual OSPI Report
OverdueRCW 28A.320.278 — School IPMAnnual Integrated Pest Management report filed with OSPI each spring. 48-hour pesticide notification required.
AHERA Annual Parent & Staff Notification
CompliantAHERA — 40 CFR Part 763.84Annual notification letter to all parents and staff about asbestos management plan. Must be distributed before school year starts.
Radon Testing
CompliantEPA Radon Guidance — 4 pCi/L action levelBiennial radon testing. EPA action level: 4 pCi/L. NRPP-certified operator required.
IPM Annual Audit
CompliantRCW 28A.320.278 — School IPMAnnual Integrated Pest Management audit. WSDA Pesticide Consultant License required for operator.
AHERA 3-Year Re-Inspection
CompliantAHERA — 40 CFR Part 763Full re-inspection of all asbestos-containing materials by an AHERA Management Planner. Required every 3 years per 40 CFR Part 763.